    Got a new Oneida Super Dust Gorilla last week. Managed to assemble it by myself, even the 'clean & jerk' of the motor/fan assembly. Stand, not wall mount.

    Now it's time to assemble some snap-lock ducting. My question is on the first piece at the DC's inlet. Do I drill and screw that too? I understand the concept of drilling/screwing the pipe onto a blastgate and pipe-to-pipe. Just was a little concerned about putting holes into my new DC.

    Any advice would be appreciated.

  2. #2
    Join Date
    Feb 2007
    Location
    Front Royal, Va.
    Posts
    1,480
    Dave, not sure what I was "supposed" to do either, but I did end up screwing the first piece off the collecter. I just followed that up with some foil tape just like all the other seams.

    Tony
    Tony

    "Soldier On"

  3. #3
    As did I. You will get over it

  4. #4
    Join Date
    Mar 2003
    Location
    SE PA - Central Bucks County
    Posts
    65,888
    At stress points, I drill with a 1/8" drill and use pop-rivets. I don't like using screws that project into the air stream as the points may tend to catch stringy material. For the rest of the joints...they just get heavy foil tape.
    --

    The most expensive tool is the one you buy "cheaply" and often...

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •