So last year I bought my house and it came with a 40 x 60 pole barn style building, only problem was I bought it with the shop as is....aka full of crap! Over the past year while taking a break from the other projects I've slowly been able to work on cleaning it out and have finally started to get down to the dirt floor and am able to start looking at what the next step is for starting to make this building more usable.
Now due to everything else I want to do to the house over the next year or two I can't really afford to drop the 4-5k it will take to put in a concrete slab for a portion of the building, so I'm strongly considering putting in a hanging/raised wood floor, similar to deck construction. This gives me the extra storage/work area now for around $300 bucks plus flooring and labor(which is free of course), and I'm fortunate enough to have lots of building so that when I get heavy enough equipment I still have plenty of room to pour a concrete pad next to it and have my choice of do I stand on wood or concrete today.
I'm planning on 15' long 2x8's doubled up for beams supported on the ends and center of span on roughly 115" centers to hang the joists on, 2x8 joists on 12" centers then put 2 runs of some type of T&G flooring, with the top run set at 90 degrees to the first. Right now I'm planning on putting in a 15' deep by 20' wide area which gives me plenty of room to store stuff off the ground(lumber), give me some extra working room and provide a base to eventually build the walls on. Assuming the joists are all grade 2 or better southern pine it gives me a 100 PSF live load rating which should be more then sufficient for what I do.
My question is I'm planning on anchoring the 2x8 beams to the 6x6 building poles where I can, but I will need to dig 4 footings/pilings for the center and end of span supports for 2 of the beams. From doing some very rough guesses the bottom of my beams will only be about 4-6" above current grade level of the floor so I'm unsure about how to support the beams. Local frost line is in that 42" down range, so I'm debating about digging a 8-10" dia hole 42 to 46" and bringing it up to the approriate height and putting the post anchor right on top of it and setting the beam directly on the piling, but that doesn't allow any wiggle room for leveling the beam. I've also considered that since it is inside and moisture should be at a minimum that I could anchor the post 10-12" below grade level, backfilling with gravel/dirt then I have more wiggle room for getting the beam level.
Any suggestions on how you would do the 4 post supports, concrete all they way up or only part of the way and put in a longer post, or some other option that I didn't mention? I'd love any additional feedback on other aspects that as well. I've attached a screenshot of the AutoCAD layout, its still a work in progress but should at least help convey the intent and give me a better chance of cutting pieces to the correct length!