I ordered a Shelix cutter head for my Delta Thickness Planer/Jointer in February. I was told it would ship May 25th. Okay.
I called at the end of May to check on the status and was told that they had an electrical problem and it would be delayed until the middle of June. Again, acceptable, I guess.
I called to checkup the third week of June.... further problems. Now it would be July 9th.
Fully prepared for further disappointment, I called today. Something let loose on the mill and the head had to be scrapped. Now the expected delivery date is July 29th at the soonest.
Does this sound like exceptionally bad luck or standard operating protocol for Byrd Tool? I'm hoping I can still expect a high quality product.