Outside shot of the pumper and the trucks. They were unloading two at a time. The cement supplier was short a truck, we were supposed to be have 6 running a loop, but they had five. It caused a little bit of down time, but not much. Ten yards per truck, and it was supposed to be one truck every ten minutes.
A little bit less than half way.
Back of the pump truck where the cement trucks unload.
Into the third corner.